Cherry Point

Cherry Creek

Description

The project generally involves milling and 2” asphalt overlay, regrading of existing roadside ditches, and replacement of various driveway culverts on the existing streets within the Cherry Point Subdivision. The project also includes the concrete channel lining of Cherry Point Gully.

Contract Amount

$4,824,400

Contractor

Triple B Services, LLP 

Project Award Date

September 14, 2020

Estimated Project Completion Date

January 27, 2022

COMPLETE

  • Street resurfacing west of Eagle Drive is complete.
  • The waterline is complete.

IN PROGRESS

  • Working on excavating culverts and ditches.

Project Map (Click to enlarge)

CherryCreekResurfacePavementPlan