Langston Boulevard extension

Langston Bridge

Description

Construct approximately one (1) mile of concrete roadway with two bridges. Includes drainage and waterline as well as excavation of amenity pond.

Contract Amount

$8,091,272

Contractor

Angel Brothers

Project Award Date

November 18, 2019

Estimated Project Completion Date

July 30, 2020

COMPLETE

  • Bridge complete.

IN PROGRESS

  • Brick and sidewalk work and clean up in backfill in progress.

Plan and Profile (click to enlarge)

Langston Plot and Profile Layout

Bridge Rendering (click to enlarge)

Langston Bridge Rendering